FAQ
Frequently asked questions about pools
What are the key factors that affect pool pricing?
Automatic pool cover (+$12,000 – $18,000+)
Distance of gas, electrical, and plumbing runs
Site access (tight access may require additional equipment costs)
Excavation and dirt removal
Amount of concrete decking/pavers (+$10 – $20 per sq. ft.)
Slope/location of pool
Shell selection
Shipping costs
Interior finish selection
Tile
Upgrade equipment options
Design complexity
All of these prices and items can vary a pool price significantly but an overall general cost breakdown is always helpful in planning your pool project.
How much is it to add a spa to my pool project in Washington?
Adding a spa to your pool project in Washington is a great way to enhance relaxation, extend your swimming season, and increase the overall value of your backyard. However, the cost of integrating a spa varies depending on factors like whether it’s raised, the level of customization, and the equipment setup.
Average Spa Cost Breakdown
In Washington, you can expect to spend between $24,000 – $35,000 to build a spa along with your pool. The price depends on:
Raised vs. In-Ground Spa – A spa that is flush with the pool is generally more affordable, while a raised spa with a spillover effect adds visual appeal but increases costs due to additional structural and plumbing requirements.
Customization – Features like LED lighting, tile finishes, and decorative stonework can all add to the overall cost.
Equipment Setup – A spa will require a heater, circulation pump, and additional plumbing, with premium automation options available for remote control via smartphone apps.
Size & Seating Capacity – The larger the spa and the more jets it has, the higher the cost due to increased material and equipment needs.
If you plan to just build a spa without a pool expect to spend 15% more due to minimums for contractors.
Do you offer financing?
We currently do not have in house financing but we have worked with Viking Capital & Lyon financial which are both well known in the pool industry.


How long does it take to build a pool in Washington?
The timeline for building a pool varies depending on the type of pool you choose and any additional features included in the project. Factors such as excavation complexity, weather conditions, permit approvals, and customizations can all impact how long it takes to complete your backyard oasis.
Fiberglass & Vinyl Liner Pools: 3 – 8 Weeks
Fiberglass and vinyl liner pools have the shortest installation timelines. Fiberglass pools come pre-manufactured and are installed as a single shell, meaning they can be placed and plumbed in as little as 3–8 weeks under ideal conditions. Vinyl liner pools require the structure to be built on-site before the liner is installed, typically taking 3–8 weeks depending on complexity.
Timelines can extend if additional elements such as a spa, automatic cover, upgraded decking, or water features are added. If extensive site work is required—such as long plumbing and electrical runs, difficult access, or additional retaining walls—the project may push closer to the 12–18 plus week range
Concrete Pools: 2 – 5 Months
Concrete (gunite or shotcrete) pools take considerably longer due to the construction process. After excavation, the structure is formed and reinforced with steel before concrete is applied, which then requires a week to cure properly. After curing, the surface finish (such as plaster or pebble) is applied, along with tile, coping, and any custom features.
A straightforward concrete pool project can take as little as 8–10 weeks, but most projects with additional decking, spas, or intricate designs extend to 3–5 months. Large projects with custom water features, infinity edges, or extensive masonry work may take even longer.
What Can Impact the Timeline?
Beyond the pool type, other factors that affect the build time include:
Permit Approvals – Some cities and counties take longer to issue permits.
Weather Conditions – Rain, snow, or freezing temperatures can delay excavation and concrete curing.
Site Access & Excavation Challenges – If heavy machinery access is limited or rock removal is required, this can slow progress.
Customization & Additional Features – Raised spas, waterfalls, tanning ledges, and high-end finishes all add extra time.
Final Thoughts
If you're planning to build a pool, understanding the timeline expectations can help set realistic goals for your backyard transformation. Fiberglass and vinyl liner pools provide faster installation (3–8 weeks), while concrete pools take significantly longer (2–5 months). Working with an experienced pool builder can help streamline the process and ensure everything is completed efficiently.